Burndown Rebuild, Braintree, Springwood Drive

Client: Mr G Fulcher Size: 3,800sqm Program: 38 weeks MDCL negotiated this contract to rebuild a burnt down terrace of two industrial units. MDCL were tasked with undertaking the full design and build and submitting the planning application. Planning was secured and the contract and price negotiated with the Loss Adjuster.  A new 11m high subdivided warehouse […]

High Bay Distribution Warehouse Extension and Mezzanine System, Sittingbourne

MDCL have negotiated with Gallery Direct Ltd to construct their new 12m high 3,758sqm extension. MDCL secured planning for the scheme. Construction started and was completed ready for  early occupation. The site required ground improvement in the form of vibro consolidated stone columns below the foundations and slab. The contract also incorporated the installation of […]

New Retail Outlets

Client: St Faith LLP Size: 15,000sqft Program: 26 weeks MDCL won this competitive tender to build 3 new retail outlets for St Faiths in Dartford, Kent. The scheme involved the striping and part demolition of an existing unit, extending and recladding, and a new build unit stand alone for Halfords. The substructure was piled with steel cased bottom […]

New Extension and Overclad of Existing Building

Client: Bryson Building Products Program:  MDCL secured planning for a small extension to the rear of a clients building and under took the over clad of the existing. The refurbishment also included the lifting and replacing of the clients yard and parking area.

Refurbishment and Extension to Existing Distribution Warehouse

Client: Kingston Estates/TNT Size: Various Program: 36 weeks MDCL won this competitive tender to re-roof, overclad and part paint the existing TNT depot and to extend the building into the yard with a new 15 door distribution facility. The works also included part replacement of the yard and internal decoration to the existing warehouse.