New Shurgard Self-storage Unit Eastbourne

Client: Shurgard Self-Storage Size: 1,650sqm Program: 38 weeks MDCL secured this tendered contract to build a new self-storage unit in Eastbourne.
New Shurgard Self-storage Unit, Barking

Client: Shurgard Self-Storage Size: 1,650sqm Program: 38 weeks MDCL secured this tendered contract to build a new self-storage unit on this very difficult piece of land in East London. The site is to be remediated and then lifted to allow the building to sit out of the flood plain.
New Logistics Scheme for Welwyn Garden City

Client: ORIGIN – Henry Boot Developments & Feldberg Capital JV Size: 6,619sqm Program: 38 weeks MDCL secured this tendered contract to build a large industrial building, subdivided into 3 units, with fully fitted offices for the speculative market place. Helping HBD realise the scheme with the initial contract to remediate the ex gasometer site. The […]
New Self Storage Unit, Brentford

Client: Storevelution Ltd Size: 1,600sqm Program: 52 weeks MDCL secured this tendered contract to build a new self storage unit in Brentford, London. The site is immediately adjacent to the Canal and thus came with its own complexities. After a review of the design and price, we were able to fulfil the clients requirements and have […]
New Industrial/Logistics Scheme, Tunbridge Wells

Client: Tavis House Size: 10,000sqm Program: 44 weeks MDCL secured this tendered contract to build two new industrial buildings, sub divided into 5 self-contained units with fully fitted offices. The site is a historical landfill and as such has its own complexities. This included a methane issue that was dealt with via positive air pressure […]
New Rugby Club, Haywards Heath

Client: Haywards Heath Rugby Club Size: 1,541sqm Program: 28 weeks MDCL secured this negotiated contract to build the new rugby club house for Haywards Heath Rugby Club. Mitchell Special Projects will undertake the full design and build of the project.
Lok’nStore Selfstorage, Bedford

Client: Lok’nStore Self Storage Size: 1,541sqm Program: 30 weeks MDCL secured this tendered contract to build a new self storage facility for Lok’nStore in Bedford. The scheme was completed on time and to budget.